Client: Illinois Department of Transportation
Location: District One, Kane County, IL
Client: Illinois Department of Transportation
Location: District One, Kane County, IL
d’Escoto has a liaison engineer and several inspectors completing the reconstruction of IL 47 at Main Street which encompassed the removal and replacement of 2 roadway bridges and multiple cell box culverts, reconstructing and raising the intersection profile of IL 47 and Main Street, resurfacing and adding a left turn lane on all four legs of the intersection, and brand-new traffic signal installation.
The existing IL 47 bridge was replaced with S.N. 045-2050 carrying 3 lanes of traffic (two through lanes and one turn lane) over Blackberry Creek using a two-stage construction safely maintaining traffic with a Temporary Soil Retention System. The new single-span bridge consists of an 8-inch reinforced concrete deck spanning roughly 82-feet long by 61-feet wide on a 10-steel beam superstructure with reinforced parapet walls extending into the approach slabs.
The profile grade elevation along IL 47 was raised 5.5-feet at the bridge location and the approach embankments were also widened to meet the bridge. The existing Main Street bridge was replaced with S.N. 045-3069 carrying 3 lanes of traffic (two through lanes and one turn lane) over Blackberry Creek using a two-stage construction safely maintaining traffic with a Temporary Soil Retention System. The new single-span bridge replaced an outdated two-span structure. It now consists of 5-inch PCC wearing surface set on seventeen precast prestressed concrete deck beams. The profile grade elevation along Main Street was raised approximately 4.5-feet at the bridge location and the approach embankments widened to accommodate the new turn lane.
d’Escoto’s inspection team consists of the Liaison Engineer, Assistant Resident Engineer, Documentation Technician, Materials Coordinator, and Inspectors.
Responsibilities included:
• Reviewing existing site conditions—documenting / photographing every aspect of site that will be impacted by construction
• On-site inspection and documentation of pay quantities, Construction & Materials Management System (CMMS) documentation, assurance of quality control of materials being used on-site
• Verifying contractor’s layout—including design changes
• Conducting a thorough review of contractor’s schedule and phasing—providing IDOT Project Manager with recommendations for improvement
• Meeting with project stakeholders including affected businesses, schools, police and fire construction work and residents to ensure impacts such as changes to Maintenance of Traffic (MOT), utilities, or construction work is coordinated and maintained
• Implementing a project documentation system—including filing logs for submittals, pay applications, scope changes, RFIs, and progress photography
• Composing Erosion-Control inspection reports
• Coordination of utility relocations
• Preparing records, maintaining documentation, submitting pay estimates, change orders